Proludic’s activity gradually recovering after the fire

Following the fire which occurred during the night between the 21st to the 22nd of March, Proludic is now turned towards rebuilding.
We would like to thank all the numerous people who, personally and professionally, have contributed to help us quickly overcome this disaster. And we would also like to include the 75 firemen who fought during several hours to contain the fire.

Concrete actions are planned during this week to ensure the resumption of our activity as soon as possible:
– The decontamination of our site
– The reconnection of our IT and telephone network
– The restoration of the servers and email inboxes

The entire administrative departments will be up and running again on Monday 3rd of April, in their own offices or in temporary modular office buildings installed on our site.
The machines necessary for the manufacturing, which were in the building destroyed by the fire, will be replaced and transferred to a 2nd building onsite, instead of the dispatch unit, which will be ensured temporarily by our logistics provider.
All our energy goes towards the gradual recovery of our industrial activity for mid-April.

Finally, the employee representatives had a meeting on Monday 27th of March to be informed concerning the actions lead and the likely consequences of this disaster, but also to be reassured concerning our entire commitment and our confidence in Proludic’s future. The representatives expressed their solidarity and their support to the directors.

Denis Le Poupon
Chief Executive Officer of Proludic